J6707-2019 - J6707 2019 Storm Sewer Repairs at Various Locations Phase 1KATS Excavating, LLC Elcor Construction, Inc Alcon Excavating Inc Pember Companies 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$3,500.00$3,500.00$3,200.00$3,200.00$6,900.00$6,900.00$19,500.00$19,500.00
2104.502REMOVE PIPE APRONEACH2$150.00$300.00$300.00$600.00$105.00$210.00$195.00$390.00
2104.503SAWING CONCRETE PAVEMENT (FULL DEPTH)L F20$25.00$500.00$10.00$200.00$5.00$100.00$6.00$120.00
2104.503REMOVE SEWER PIPE (STORM)L F70$22.00$1,540.00$5.00$350.00$8.00$560.00$23.00$1,610.00
2104.503SALVAGE METAL RAILINGL F40$18.75$750.00$12.00$480.00$6.50$260.00$8.00$320.00
2104.503SAWING BITUMINOUS PAVEMENTL F20$25.00$500.00$5.00$100.00$5.00$100.00$3.50$70.00
2104.507REMOVE RIPRAP (P)C Y264$3.79$1,000.56$12.00$3,168.00$15.25$4,026.00$25.50$6,732.00
2104.518REMOVE CONCRETE SIDEWALKS F401$4.48$1,796.48$1.00$401.00$1.70$681.70$1.60$641.60
2104.518REMOVE BITUMINOUS WALKS F299$4.01$1,198.99$0.50$149.50$1.20$358.80$1.10$328.90
2105.507COMMON BORROW (CV) (P)C Y369$12.00$4,428.00$17.00$6,273.00$19.80$7,306.20$29.00$10,701.00
2301.602DRILL & GROUT DOWEL BAR (EPOXY COATED)EACH7$30.00$210.00$18.00$126.00$20.45$143.15$11.15$78.05
2501.50236" RC PIPE APRONEACH2$1,850.00$3,700.00$2,637.00$5,274.00$2,050.00$4,100.00$3,100.00$6,200.00
2503.54136" RC PIPE SEWER DES 3006 CL IIIL F208$170.56$35,476.48$164.00$34,112.00$131.75$27,404.00$179.00$37,232.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 4EACH1$5,582.00$5,582.00$8,690.00$8,690.00$6,390.00$6,390.00$6,400.00$6,400.00
2511.501RANDOM RIPRAP CLASS IVC Y75$33.27$2,495.25$37.00$2,775.00$63.00$4,725.00$80.00$6,000.00
2511.504GEOTEXTILE FILTER TYPE 4S Y112$6.69$749.28$1.00$112.00$2.00$224.00$3.75$420.00
2521.5188" CONCRETE WALK-REINFORCEDS F401$12.22$4,900.22$17.00$6,817.00$18.20$7,298.20$13.00$5,213.00
2540.603INSTALL METAL RAILINGL F40$30.00$1,200.00$30.00$1,200.00$21.00$840.00$35.00$1,400.00
2563.601TRAFFIC CONTROLLS1$200.00$200.00$500.00$500.00$3,352.00$3,352.00$2,900.00$2,900.00
2573.502STORM DRAIN INLET PROTECTIONEACH2$150.00$300.00$250.00$500.00$170.00$340.00$160.00$320.00
2573.503FLOTATION SILT CURTAIN TYPE MOVING WATERL F60$8.33$499.80$30.00$1,800.00$28.41$1,704.60$30.00$1,800.00
2573.503SILT FENCE; TYPE HIL F60$5.50$330.00$4.00$240.00$5.65$339.00$3.70$222.00
2574.507COMMON TOPSOIL BORROWC Y127$12.00$1,524.00$29.00$3,683.00$36.60$4,648.20$45.00$5,715.00
2575.523EROSION CONTROL BLANKETS CATEGORY 3S Y762$2.89$2,202.18$3.00$2,286.00$1.90$1,447.80$2.75$2,095.50
2575.604SITE RESTORATION TYPE 2S Y762$1.96$1,493.52$2.00$1,524.00$1.45$1,104.90$3.50$2,667.00
S100.585BITUMINOUS TRAIL RESTORATION S Y32$109.38$3,500.16$75.00$2,400.00$85.00$2,720.00$100.00$3,200.00
 Totals for project J6707-2019 $79,876.92 $86,960.50 $87,283.55 $122,276.05
 
Contract Total:$79,876.92$86,960.50$87,283.55$122,276.05